Underloads remained less than 2% of the total of which some can be attributed to weather events, and major overloads remained suppressed.
The performance improvement within just the first week of implementation was notable with the payload distribution tightening significantly (Figure 1). There was also a significant reduction in underloads and overloads as trucks were loaded closer to their rated payload capacity.
While the average payload to target capacity before and after increases by less than 1% (98.57% to 99.18%), the biggest gain was how the operators were achieving that average compliance value. The standard deviation between truckloads dropped from 11.87% to 8.09%, confirming that the operators used the Argus system to load more effectively. Major overloads dropped off completely, and underloads shrink significantly.
Prior to Argus, 20% of truckloads left the shovel under 90% capacity, with the average payload for underloaded trucks 81.5%. This equates to 65 tonnes short of a full load. Over a week, with an average of 5,500 truckloads on a predominantly CAT 797 fleet, this would result in an additional 71,500 tonnes moved at no additional cost between the 3 CAT 495 shovels.
On average, a CAT 797 moves 225,000 tonnes of material per month (based on May 2020). The above increase in achieving target on the 20% of underloaded trucks equates to 306,000 additional tonnes moved per month or parking a CAT 797 truck.
Major overloads reduced from 8% to 0.4% in the first week. Given that trucks that leave the pit with major overloads result in a fine, the reduction results in immediate cost savings.
The results in Figure 2 show the first six weeks of operation for the three CAT 495 shovels. The baseline data was collected utilizing the truck scale information.
This reflects an adoption period where the operators continually improved the payload distribution around the target payload. During this period, there is a trend toward moving slightly above target (105% vs 100%) loads, and a complete reduction of overloading.
- Week 1 indicated quick adoption to the system. There were still 23 major overloads (>120%), and 274 loads below target (<90%). 92% of loads were within target (90-110%).
- By week 3, overloads (>120%) were reduced to 2, and underloads (<90%) were reduced to 132 for the week. 97% of loads were within target (90-110%).
- By week six, overloads (>120%) were at 2, underloads (<90%) were at 73, and loads in target (90-110%) were 98% of total.
On a predominantly CAT 797 truck fleet, correctly loading trucks would create an additional 11,100 tons of material moved during the week. This equates to an additional 577,000 tons moved per year on the three CAT 495 shovels, without any additional haulage equipment, effort, or training.